Shetland turbines get go-ahead

1 August 2014


Scottish judges have removed the last legal obstacles to the 370MW Viking project on the Shetland Islands.
A judgment from October 2013 that the Scottish government should not consent to the product until an electricity generating licence had been granted was overturned, as was one stating that the likely effects of the 103-turbine installation on migratory birds had not been adequately addressed.
The former ruling had raised concerns that setting a precedent whereby licenses had to be granted before projects could be approved (contrary to standard UK practice) might have affected other, similar undertakings.
A potential load factor of up to 50% would make the scheme, which is a joint venture between utility SSE and Viking Energy, the most productive of its kind in Europe.



Privacy Policy
We have updated our privacy policy. In the latest update it explains what cookies are and how we use them on our site. To learn more about cookies and their benefits, please view our privacy policy. Please be aware that parts of this site will not function correctly if you disable cookies. By continuing to use this site, you consent to our use of cookies in accordance with our privacy policy unless you have disabled them.